| Start Date |
Week # |
Activity |
Description of Activity |
Volunteers needed |
| 17/18 Aug |
week 0 |
Deconstruct |
Tear out interior Drywall / remove insulation |
SVSU Students |
| |
|
|
Complete tear out and remove exterior siding |
SVSU Students |
| |
|
|
|
|
| 24-Aug |
week 0 |
Pre-build |
Const. Committee Review / Purchase Permits / plan |
Committee / M. Johns |
| |
|
|
|
|
| 24-Aug |
week 1 |
Saturday 1 |
Remove Chimney, siding, fill dumpster, repair wall by |
14+ volunteers needed |
| |
|
|
chimney, install Dow foam, remove cement porches |
|
| |
|
|
|
|
| 12-Sep |
week 2 |
Saturday 2 |
Build bump outs into garage, remove LR wall, finish |
15 - 18 volunteers needed |
| |
|
|
install foam, install windows, install doors, start |
|
| |
|
|
siding, furring to basement walls for insulation |
|
| |
week 2a |
weekday |
Heating, Plumbing, Electrical contractors in house |
No volunteers needed |
| |
" |
weekday |
Order appliances, electric panel, waterheater, etc |
Site manager |
| |
|
|
|
|
| 19-Sep |
week 3 |
Saturday |
Complete siding, build porch/deck, complete base- |
15 - 18 volunteers needed |
| |
|
|
ment insulation/foam |
|
| |
week 3a |
weekday |
Pro Contractors complete rough mechanical |
No volunteers needed |
| |
" |
weekday |
Call for rough inspections |
No volunteers needed |
| |
" |
weekday |
Homeowner to choose carpet / flooring, countertop |
Partner Family |
| |
|
|
|
|
| 26-Sep |
week 4 |
Saturday |
Complete exterior jobs/porches, install insulation |
15+ volunteers needed |
| |
week 4a |
weekday |
TBD - spray foam or fiberglas? |
TBD /Contracted? |
| |
|
|
Begin Drywall installation - by professional ? TBD |
Professional |
| |
|
|
|
|
| 3-Oct |
week 5 |
Saturday |
Hang drywall by volunteers TBD |
15+ volunteers needed |
| |
week 5a |
weekday |
Finish drywall |
Professional |
| |
|
|
|
|
| 10-Oct |
week 6 |
Saturday |
Complete misc jobs / Prep & begin painting, etc |
12 + volunteers needed |
| |
|
|
trim trees, landscape, exterior jobs completed |
|
| |
week 6a |
weekday |
Complete misc jobs / painting, etc |
4 - 6 volunteers needed |
| |
|
|
|
|
| 17-Oct |
week 7 |
Saturday |
Install cabinets, interior doors, closets, trim |
8 - 12 volunteers needed |
| |
week 7a |
weekday |
complete mechanical, plumbing, electrical installation |
Professional |
| |
" |
" |
complete trim, finish misc jobs, etc |
TBD |
| |
|
|
|
|
| 26-Oct |
week 8a |
weekday |
Homeowner to choose carpet / flooring, countertop |
Partner Family/ Site Mgr/ED |
| |
|
|
paint colors, etc |
|
| |
|
|
|
|
| 26-Oct |
week 8a |
weekday |
Spray foam contractor on site |
Efficient Foam |
| |
|
|
Drywall delivered - afternoon |
|
| 27-Oct |
week 8a |
weekday |
Begin Drywall installation - |
Brian Finnegan |
| |
|
weekday |
Hang drywall by volunteers TBD |
6+ volunteers needed |
| |
|
|
|
|
| 30-Oct |
week 8a |
weekday |
Begin to finish drywall - mud |
Professional |
| |
|
|
|
|
| 31-Oct |
week 9 |
Saturday |
Drywall finishing continues - no other work scheduled |
no volunteers needed |
| 6-Nov |
week 9a |
Friday |
pre dedication day clean-up & prep |
8 volunteers needed |
| |
|
|
|
|
| 7-Nov |
week 10 |
Saturday |
Dedication Ceremony - 8:30 am followed by painting |
Large crowd plus- |
| 7-Nov |
week 10 |
Saturday |
Prep & begin painting, etc |
12 + volunteers needed |
| |
|
|
|
|
| 9-Nov |
week 10a |
weekday |
Complete misc jobs / painting, etc |
8 - 10 volunteers needed |
| |
" |
" |
Install cabinets, interior doors, closets, trim |
|
| |
" |
" |
complete trim, finish misc jobs, etc |
|
| |
" |
" |
install kitchen/bath cabinets |
|
| |
|
|
|
|
| 12-Nov |
week 10a |
weekday |
complete mechanical, plumbing, electrical installation |
Professional |
| |
" |
" |
Carpet / vinyl floor installed |
Professional |
| |
" |
" |
Install appliances |
3 volunteers needed |
| |
|
|
|
|
| 14-Nov |
week 11 |
Saturday |
Final touches and clean-up |
10+ volunteers needed |
| |
week 11a |
weekday |
Final inspections |
Site/Project Contractor/ |
| |
|
|
|
Building inspectors |